November 19, 2021
The contractor has completed all paving and roadway striping.  Traffic control devices has been removed and the intersection has been opened to traffic.  Over the coming weeks the contractor will be working on minor work items and removal of the remaining signage.

 

September 27, 2021
This week as part of Phase 5, the contractor continued installation of the water main including testing and tie-ins. This work should be completed this week.  The contractor is planning on transitioning to Phase 6 the first week of October, this will be the final phase of the project.  The project is on schedule and anticipated to be complete by December 2021.

 

July 22, 2021
Reytec Construction Resources, Inc. has implemented a traffic control switch as part of Phase 2B of construction. During Phase 2B of the project, drivers and pedestrians should expect to see the following lane closures and traffic changes:

  • South Staples Street, in the southbound direction, will be reduced to one lane from Booty Street to South Alameda Street. Thru traffic will be shifted to the northside of South Staples Street (northbound lanes) between South Alameda Street and the Six Points Intersection. Thru traffic will remain on the northside across the Six Points intersection and will be shifted to the southside of South Alameda Street at the Palmero Street intersection.
  • South Alameda Street will be closed from the Six Points intersection to Palmero Street, in the southbound direction only.
  • South Alameda Street will be reduced to one lane from Clifford Street to the Six Points intersection, in the northbound direction only.
  • The “Right Only” travel lane between South Alameda Street and the Six Point Intersection will be reopened to allow right turns onto Ayers Street.
  • South Staples Street will be closed from the Six Points intersection to 10th Street, in the southbound direction only. 
  • South Staples Street will be reduced to one lane between 10th Street and the Six Points intersection, in the northbound direction only.
  • 10th Street, between Ayers Street and South Staples Street, has been reconstructed, and traffic will flow has been changed to ONE-WAY in the southbound direction (Ayers Street to South Staples Street).
  • Ayers Street will be closed to thru traffic between 10th Street and the Six Points intersection, in the eastbound direction only.
  • The “Left Turn Only” lane along westbound Ayers Street will be closed at the Six Points intersection.
  • Sidewalks will be closed within the work zone.

 

June 18, 2021
The Six Points Project moves ahead this week, as Reytec Construction actively works on Phase 1B (10th between Ayers and Staples) & 1C (Utility Work on Staples) of the project. Currently, the sewer line and 8” waterline at 10th street has been installed, tested, and passed inspection. Concrete curbs, gutters, and sidewalks along with additional parking is also being installed as part of Phase 1B. Next week, the 72” wastewater manhole  will begin installation as part of Phase 1C.