Skip to main content
Emergency Alert

Stage 1 Water Restrictions in Effect
Click here to find your watering day and more. 


2022 Tax Rates
View the latest Notice of Public Hearing and the Notice About 2022 Tax Rates.


PROJECT MAPS 


Project Overview (Project #18014A) »
A large technical drawing showing the scope of the rebuild.

Construction Sequence Map »
A map of the construction area and color-coded phases.

CCRTA Bus Route 17 Detour »
Route 17 Carroll/Southside Temporary Detour from Corona Dr. to Holly Rd. Updated January 12, 2021.

Traffic Control Map for Phase’s 2 and 3 »
A satellite view of Phase's 2 and 3, updated July 2020.

Traffic Control Sections »
Cross-sections of the street during different phases, including work area and temporary travel lanes.

________
 

PROJECT FACTS


Project Consultant Architect:              Freese and Nichols, Inc.

City Project Manager:                           Lj Francis, P.E., M.ASCE

Contractor:                                            Reytec Construction Resources, Inc.

Construction Inspectors:                     Joe Sandoval, Oscar Newsmith

Liquidation Damages:                           $2,500/day

Award Date:                                           July 2019

Anticipated Construction Start:           September/October 2019

Substantial Completion:                       May 2021

Final Completion:                                  June 2021

Total Project Value:                               $14,400,000

________


PROJECT SCOPE

  • The project will focus on major replacements of underground utilities, including a 36” water transmission main, 30” wastewater trunk main, and major storm infrastructure.
  • The roadway will be reconstructed with concrete. 
  • New or upgraded signals at Holly, Bonner and Corona are included with the project.
  • The project is paid for through Type B funds
  • Construction duration is 18 months with an option for the Contractor to work 24 hours if needed.
  • Full closure of Everhart at Bonner is expected early in the project to accelerate underground utility crossing replacement.