PROJECT MAP
Project Overview (Project #E15106) »
A large technical drawing showing the scope of improvements.
________
PROJECT FACTS
Project Consultant Architect: Lockwood, Andrews & Newnam, Inc
City Project Manager: Sandra L. Gomez, P.E. and Larry H. Wenger Jr., P.E.
Contractor: Haas-Anderson Construction, LTD
Construction Inspector: Gerald Lopez
Liquidation Damages: $1000/day
Award Date: August 2019
Anticipated Construction Start: January 2020
Anticipated Completion: May 2022
Total Project Value: $11,016,599.50
_______
PROJECT SCOPE
- Widening approximately 3,000 linear feet of Ayers Street to accommodate for the addition of a continuous turn-lane and right turns at SPID, McArdle, and Gollihar
- Convert existing roadside drainage ditches to underground culverts with construction of a 36” drainage pipe
- Utility improvement for water, wastewater, and gas
- New curb and gutter, sidewalks and ADA ramps
- Extension of ADA compliant sidewalk along the east side of Ayers Street from Gollihar to Port Avenue that is partially funded by RTA
- Construction duration is about 28 months