PROJECT MAP 

Project Overview (Project #E15106) »
A large technical drawing showing the scope of improvements.

Traffic Flow Map »

________

PROJECT FACTS

Project Consultant Architect:              Lockwood, Andrews & Newnam, Inc

City Project Manager:                           Sandra L. Gomez, P.E. and Larry H. Wenger Jr., P.E.

Contractor:                                             Haas-Anderson Construction, LTD

Construction Inspector:                        Gerald Lopez

Liquidation Damages:                           $1000/day

Award Date:                                            August 2019

Anticipated Construction Start:           January 2020

Anticipated Completion:                       May 2022

Total Project Value:                               $11,016,599.50

_______
 

PROJECT SCOPE

  • Widening approximately 3,000 linear feet of Ayers Street to accommodate for the addition of a continuous turn-lane and right turns at SPID, McArdle, and Gollihar
     
  • Convert existing roadside drainage ditches to underground culverts with construction of a 36” drainage pipe
     
  • Utility improvement for water, wastewater,  and gas
     
  • New curb and gutter, sidewalks and ADA ramps
     
  • Extension of ADA compliant sidewalk along the east side of Ayers Street from Gollihar to Port Avenue that is partially funded by RTA
     
  • Construction duration is about 28 months