Construction duration is expected to be 18 months with an option for the Contractor to work 24 hours if needed.

Photo of Sign at Everhart Construction Site.

Photo of sign at Everhart Construction Site.

________

Award Date: July 2019

Anticipated Construction Start:  September 30th, 2019

Early Milestones: Lane closures for northbound Everhart Road from Holly Road to Cain Drive for underground utility work.

Substantial Completion: May 2021

Final Completion: June 2021